INDUCTION CHECKLIST
To be conducted by Site Supervisor at commencement of job & throughout job as required.
Review Hazards & Risk Assessments: SWMS reviewed for high risk works
All workers on site incl. subcontractors must sign on to this induction register & relevant SWMS. Subcontractor works SWMS must be available on site also.
Discuss Public Safety & Access: Site fencing set up around work site. Signage in place at main entry
Discuss Traffic Management: Delivery access & site routes planned. Other traffic management as per TMPs
Review Personal Protective Equipment Requirements: As per this PMP. High Vis tops & Safety Boots to be worn at all times. Hard hats must be worn when working in trenches deeper than 1m or when under machinery.
Review Plant & Equipment Safety Instructions: As per SWMS & Daily Plant inspection books.
Discuss any Hazardous Materials or Dangerous Goods: SDS register & hard copies kept in site office.
Discuss Program Status & any Immediate Commitments: Program kept in site folder in site office. Discussed as required & at weekly site meetings.
Discuss the management of external resources: All subcontractors must read & sign this induction & relevant SWMS prior to commencing work on site. All subcontractor SWMS must be kept on site also
Discuss Emergency Procedures & Incident Reporting: All incidents & injuries are to be reported to Site Supervisor immediately. Relevant WHS forms in the site folder are to be completed & sent in to / reported to main office. Emergency procedures as per this PMP.
Review WHS / Env / QA requirements, target & objectives for project: As detailed in the PMP, EMP & PMP developed for this project & kept in site folder.
Explain any New Procedures, Work Practices, Legislation: As required
Other Site-Specific Issues: To be discussed daily at pre-start toolbox meetings.
SEDMP: Plan kept in site folder – 1351
Complete Emergency Drill
General Comments/Observations/Requirements:
Location of 1st Aid Kit – In site office & lunch room + in all ARCS plant & vehicles on site.
Amenities / Housekeeping – As required
Location of SDS – Site office
Emergency numbers & meeting point – As detailed & displayed on site office wall.
Induction Leader: Joel Bailey